280th Street W. (County Road 86) Roundabouts

​​​​​​​​County Projects 86-44 a​nd 86-43

Dakota County will construct two single lane roundabouts. The roundabout will be at:

  • 280th Street W. (County Road 86) and Chippendale Avenue (Highway 3) within Castle Rock and Waterford townships
  • 280th Street W. (County Road 86) and Randolph Boulevard/Emery Avenue (Highway 56) within Randolph and Hampton townships

The purpose of the project is to improve safety and traffic operations.  Construction includes constructing single lane roundabouts, restriping, and drainage improvements.

Construction ​progress​

The intersection of County Road 86 and Highway 3 is now open. Please drive with caution as this is still an active construction site. Thank you for your patience during these road improvements.

Community engagement

The county ​hosted a public open house on Sept, 16, 2024 at the St. Mark's Lutheran Church, 28595 Randolph Blvd., Randolph.​

The county hosted a public open house on Monday, Aug. 11, 2025 at the St. Mark's Lutheran Church, 28595 Randolph Blvd., Randolph.

County Road 86 project map.

Project timeline

  1. Preliminary and final engineering design

    February 2024–spring 2025

  2. Public engagement

    Fall 2024–spring 2025

  3. Right of way acquisition

    Fall 2024–summer 2025

  4. Construction at 280th Street W. (County Road 86) and Randolph Boulevard/Emery Avenue (Highway 56)

    May-August 2026

  5. Construction​ at 280th Street W. (County Road 86) and Chippendale Avenue (Highway 3)​

    May-November 2026

For more​​ informa​tion

Dakota County Roundabout Education

Email upd​ates

To receive email updates for this project, email Stacy Reilly at stacy.reilly@co.dakota.mn.us. Please include “CP  86-43, 86-44 Updates" in the subject line.​

For more information, contact:
Transportation
952-891-7100