Babcock Trail (County Road 73) Trail Improvements

Dakota County and the City of Inver Grove Heights will construct a trail on the east side of Babcock Trail. The trail is between Upper 55th Street and Interstate 494.

Project o​verview

The project includes:

  • Trail on the east side of Babcock Trail
  • Curb and gutter on the east side of Babcock Trail
  • New storm sewer
  • Accessibility improvements
  • Partial repaving of Babcock Trail

Road closures and detours

Babcock Trail and Cenex Drive have reopened in all directions. 

Construction p​rogress

Week of Aug. 31

  • Placing topsoil and completing seeding
  • Paving final layer on Babcock Trail

Week of Sept. 7

  • Restriping of Babcock Trail throughout the project area
  • Installing signage throughout the project area
County Road 73 project map.

Project timeline

  1. Design

    2024

  2. Right of way acquisition

    2025

  3. Construction

    June-September 2026

Con​tact

If you have questions or comments on the project, please contact: ​​

Paul Merchlewicz, PE
City Engineer, Inver Grove Heights
651-450-2572